GAO Report: Navy Plan to Upgrade Pearl Harbor Shipyard Falls Short

By News Release @ 1:05 AM :: 4245 Views
 

Key Actions Remain to Improve Infrastructure to Better Support Navy Operations

GAO-20-64: Published: Nov 25, 2019. Publicly Released: Nov 25, 2019

Fast Facts

The Navy’s public shipyards are critical to maintaining its nuclear-powered aircraft carriers and submarines, as well as supporting its operations around the world. In 2017, we found the shipyards were in poor condition and not meeting the Navy’s needs. In response, the Navy developed a 20-year, $21 billion plan to fix them.

However, we found the preliminary plan’s cost estimate is likely understated by billions of dollars. It is missing key elements such as adjustments for inflation, environmental remediation, and utility upgrades.

We recommended that the Navy include these missing elements when it produces its more detailed cost estimate.

Link: Highlights

Link: Recommendations  

PDF: Full Report

AP: Report: Public shipyards in need of improvements