Hawaiian Electric Companies propose using natural gas with modernized generation for a lower cost, cleaner path to 100 percent renewable energy
- Up to $3.7 billion estimated customer savings
- Over 8 million barrels less oil imported annually starting in 2021
- Four million tons less greenhouse gas emissions for a smaller carbon footprint
- Transition to renewable energy with greater reliability and 30 percent better efficiency through a modernized generation fleet and retirement of older, oil-fired units
News Release from Hawaiian Electric
HONOLULU, May 18, 2016 - The Hawaiian Electric Companies today asked the Hawaii Public Utilities Commission (PUC) to review and approve a proposed contract with Fortis Hawaii Energy Inc. to import liquefied natural gas (LNG) for electricity generation on Oahu, Hawaii Island and Maui.
The contract, the culmination of a request for proposals issued two years ago, would provide a cleaner, low-cost fuel to replace oil in the transition to achieving Hawaii's 100 percent renewable portfolio standard by 2045. If approved, Hawaiian Electric envisions beginning use of natural gas in 2021 with a 20-year contract ending as Hawai'i approaches its 100 percent renewable energy goal.
"We are committed to achieving our state's 100 percent renewable energy goal with a diverse mix of renewable resources," said Ron Cox, Hawaiian Electric vice president for power supply. "As we make this transition, LNG is a cleaner-burning alternative that potentially can provide billions of dollars in savings and stabilize electric bills for our customers compared to continuing to rely on imported oil with its volatile prices. LNG is a superior fuel for the firm generation needed to keep electric service reliable as we increase our use of variable renewables like solar and wind."
At the same time, Hawaiian Electric is asking the PUC for authorization to construct a modern, efficient, combined-cycle generation system at the Kahe Power Plant to get the maximum customer benefits from use of cleaner, less expensive natural gas; better support integration of renewable energy; and facilitate retirement of three older, oil-fired generators at the Kahe Power Plant.
Critical timing for customer benefits
The Fortis Hawaii contract is also contingent on PUC approval of the merger of Hawaiian Electric with NextEra Energy. This project requires substantial upfront financial support and expertise that NextEra Energy can provide. If the merger is not approved, the Hawaiian Electric Companies would still be interested in pursuing on their own the benefits of LNG for customers, but the companies would need to negotiate a new contract which likely would mean lower, delayed savings for customers and delayed benefits for the environment.
Significant projected savings and environmental benefits for Hawaii
Hawaiian Electric estimates the natural gas contract and greater efficiencies from modernized generation could save electricity customers from $850 million to $3.7 billion through 2045, depending on future oil prices. At the same time, annual oil imports for electricity generation would be reduced by over 8 million barrels, or 80 percent, as soon as 2021. Hawaii's carbon footprint would be reduced by significantly cutting greenhouse gas emissions. The reduction of over 4 million tons in carbon dioxide emissions alone equals taking more than 80 percent of Hawaii's passenger vehicles off the road.
Savings on electric bills for typical residential customers using 500 kilowatt-hours a month, when compared to alternative generation planning scenarios using oil, could be as much as $390 a year for Oahu customers. Savings for Hawaii Island and Maui customers are estimated at $100 and $15 per year, respectively.
The savings take into account the estimated $341 million cost of converting existing generating units to use natural gas at Kahe Power Plant on Oahu, Maalaea on Maui, and Keahole and Hamakua Energy Partners on Hawaii Island, and the estimated cost of $117 million for LNG containers. The logistics system to deliver and offload the LNG will not require development of new infrastructure off- or on-shore in Hawaii.
"We know Governor Ige has expressed opposition to importing LNG," Cox said. "However, we have just reached contract terms with a supplier after a long negotiation and now have much more than a theoretical plan for the governor, Public Utilities Commission, energy stakeholders and the public to consider. We believe we have a responsibility to put forward an option that has significant economic and environmental benefits for the people of Hawaii, and that addresses some of the Governor's concerns.
"This proposal, negotiated with the added expertise and experience of NextEra Energy as an advisor, will support achieving our 100 percent renewable energy goals. It will allow us to integrate increasing amounts of renewable energy at much lower cost while providing more reliable service for our customers. Further, our plan keeps new LNG infrastructure, both on- and off-shore, to a minimum and preserves flexibility to reduce LNG imports as renewable energy increases," Cox said.
For 50 years, natural gas has been safely transported around the world in liquefied form for use in power generation. It is subject to strong international, national and local regulation and monitoring for safety and environmental protection. For Hawaii, this proposal will provide enhanced security of fuel supply by avoiding the risk of sourcing fuel from more remote and politically unstable locations.
Under the proposed plan, Fortis -- a leader in the North American electric and gas utility business -- would liquefy the gas piped from northeastern British Columbia at its Tilbury facility in Delta, near Vancouver. The LNG would be transported from British Columbia to Hawaii in mid-sized LNG carrier ships.
The Hawaiian Electric Companies would use natural gas in power plants to generate the electricity delivered via island power grids to homes and businesses where customers will use the same electric water heaters, stoves, refrigerators and other appliances as today. As with all fuel purchases and purchased power, the actual cost of the natural gas would be passed directly to customers on electric bills, without mark-up or profit to the Hawaiian Electric Companies.
Flexibility for the future
The price of natural gas will be tied to market prices in British Columbia, not to oil prices, providing lower, less volatile prices, especially as today's low oil prices rise, as expected. The contract provides for lower payments if the Hawaiian Electric Companies decide to take less than the full capacity commitment of LNG; for example, if more renewable resources come online more quickly than expected.
The vessels and trucks (owned by others) and the containers to import LNG under this plan are modular and movable so a significant portion can be resold or repurposed when no longer needed to serve power generation in Hawaii. The carrier ships, barges and possibly the trucks to deliver LNG to power plants will be fueled by LNG, further reducing oil use in Hawaii.
Modernizing generation for lower fuel costs and more reliable service
To gain the greatest savings for customers and better ensure reliable service as the integration of renewable energy increases from variable sources like sun and wind, Hawaiian Electric also proposes to modernize the generation fleet on Oahu. Three steam generators at the Kahe Power Plant (Units 1-3) would be deactivated by the end of 2020 when each will be over 50 years old and replaced with an efficient, combined-cycle generation system located at the plant further from the shoreline than the existing units. The location provides greater energy security, for example from tsunamis, and a less visible profile.
The combined-cycle system would include three modern, quick-starting, fast-ramping combustion turbines with three heat recovery steam generators and a single steam turbine to generate power using the waste heat that is recovered. This flexible, fuel-saving combination would be 30 percent more efficient than the deactivated generators. This modern generation is needed to balance the increasing amounts of variable renewable energy being added as Hawaii transitions to 100 percent renewable energy. The combined-cycle system will be capable of using renewable biofuels.
Measured against current levels, the combined generation modernization and natural gas plan produces lower carbon dioxide emissions by over 4 million tons when fully operational.
To secure these benefits for customers as quickly as possible and ensure reliable service as the new combined-cycle system replaces old generating units, Hawaiian Electric is seeking Public Utilities Commission permission to construct the new generating system with an estimated in-service date of January 2021.
In the Commission's Inclinations on the Future of Hawaii's Electric Utilities (April 28, 2014), the PUC recognized the need for generation modernization and stated that Hawaiian Electric Companies need to "move with urgency to modernize the generation system as delays are lost savings opportunities" and should "expeditiously...[m]odernize the generation to achieve a future with high penetrations of renewable resources." (emphasis added)
The proposed combined-cycle system is intended to be responsive to these PUC concerns. The estimated cost for modernized generation at Kahe Power Plant and to interconnect the new system to the grid is $859 million. This cost is factored into the overall savings projected for the LNG plan.
The Hawaiian Electric Companies' plan also proposes using natural gas in two remaining Kahe units (5-6) and the Kalaeloa Partners power plant on Oahu. In addition, natural gas is proposed for use on Maui at Maalaea Power Plant and on Hawaii Island at Keahole Power Plant and the Hamakua Energy Partners plant. Natural gas could also be used at the planned Schofield Generating Station and other future generating sites to provide savings for customers.
An Environmental Impact Statement will be prepared. In addition to thorough Public Utilities Commission review with input from the Consumer Advocate, community stakeholders and others will have many opportunities for input through the extensive environmental review and permitting approval process.
Additional details are available in the accompanying fact sheet.
---30---